PROJECT PHOENIX · SAP S/4HANA · SAMPLE

Executive command center

Implementation control for decisions, risks, readiness and executive alignment.

Overall health At Risk52 days to go-live
!
Leadership action required

Data conversion, tester capacity and three open critical/high defects threaten the October 19 go-live.

Review actions →
Days to go-live52October 19, 2026
Milestones at risk1Build Exit · Aug 30
Critical RAID44 require attention
Critical / high defects3Open Sev 1 or Sev 2
Overdue decisions1SteerCo action

EXECUTIVE ATTENTION

Decisions and escalations

4 urgent
D
Approve weekend SMEs for cutover rehearsal

Transformation SteerCo · Due Aug 25

Overdue
D
Approve two-week UAT surge staffing

Transformation SteerCo · Due Aug 29

Pending
I
Business tester availability below plan

Alicia Grant · UAT Lead

Escalated
R
Legacy customer cleansing behind plan

Maya Chen · Data Lead

Escalated

CONTROL DIMENSIONS

Readiness profile

ScheduleWatch
BudgetWatch
ScopeOn track
QualityWatch
ChangeIntervention
CutoverWatch

TRANSFORMATION LIFECYCLE

Build Exit is the active gate

Next review · Aug 30
MobilizeComplete
DesignComplete
3BuildActive
4TestUpcoming
5DeployUpcoming
6HypercareUpcoming
3 open conditionsData-conversion recoveryUAT capacityCritical-defect containment

WEEK OF AUGUST 24, 2026

This week's command panel

The outcomes and decisions that move the program this week.

At Risk

Top priorities

3 outcomes
01Restore cleansing throughputMaya Chen · Due Aug 28At risk
02Secure protected UAT capacityAlicia Grant · Due Aug 29Decision
03Contain open Sev 1 / Sev 2 defectsFunctional Leads · Due Aug 29In progress

Milestones and meetings

Next 3
Data conversion recovery checkpointOwner · Maya Chen
UAT capacity and defect triageOwner · Alicia Grant
Build Exit Gate ReviewOwner · Program Director

Decisions required

1 overdue
DecisionOwnerRequired byImpact if delayedStatus
Weekend SMEs for cutover rehearsalTransformation SteerCoAug 25Weaker rehearsal coverageOverdue
Two-week UAT surge staffingTransformation SteerCoAug 29Compressed testing and retestPending

Progress since last update

Security defect closedUAT-009 passed retest
Cutover ownership assignedContact validation in progress
Blueprint evidence retainedGate remains passed

GOVERNANCE & PLANNING

Decision rights and stage gates

Evidence-led governance that makes accountability visible.

01

Project intake

Diagnostic, complexity assessment and mobilization baseline.

Ready →
02

Program charter

Outcomes, scope, governance, constraints and measures.

Approved →
03

RACI

Decision accountability across business and technology.

Current →
04

SteerCo

Executive agenda, decisions, actions and briefing narrative.

2 decisions →

Stage-gate tracker

1 in review
GatePhaseDecision ownerTargetExit criteriaStatus
Mobilization ExitInitiateExecutive SponsorMay 15MetPassed
Blueprint ExitBlueprintDesign AuthorityJul 10MetPassed
Build ExitBuildProgram DirectorAug 303 conditionsIn review
UAT ExitTestProcess OwnersSep 25Not metNot started
Go / No-GoCutoverTransformation SteerCoOct 16Not metNot started

DELIVERY & RISK

Control risk, quality and readiness

One operational view of what threatens delivery and what happens next.

Executive RAID

4 critical
IDRecordTypeOwnerDueRAG
DEC-004Approve weekend SMEs for cutover rehearsalDecisionTransformation SteerCoAug 25Red
I-003Business tester availability below planIssueAlicia GrantAug 26Red
R-001Legacy customer cleansing behind planRiskMaya ChenAug 28Red
DEC-007Approve two-week UAT surge staffingDecisionTransformation SteerCoAug 29Red
R-002CPI interfaces may miss performance thresholdRiskDaniel BrooksSep 2Amber

Open critical / high UAT defects

3 open
IDDefectModuleSeverityOwnerStatus
UAT-017Sales order posting fails after credit releaseSalesSev 1Ethan ColeNew
UAT-024Payroll interface drops overnight shift premiumHRSev 2Omar ReedRetesting
UAT-021Duplicate vendors created during replicationProcurementSev 2Nina PatelIn progress

PEOPLE & CHANGE

Adoption is a delivery condition

Connect stakeholder commitment, communications, training and benefits to go-live readiness.

Intervention
Critical stakeholders82 require re-engagement
Training readiness64%Below plan
Comms delivered7/9Current cycle
Benefits validated5/72 pending owners
01

Stakeholder intelligence

Influence, commitment, impact and intervention actions.

2 interventions →
02

Change engine

Readiness assessments, change impacts and adoption plans.

At risk →
03

Communications hub

Audience, message, channel, owner and response tracking.

2 upcoming →
04

Benefits realization

Measures, baselines, targets, owners and evidence.

2 pending →

TCC INTELLIGENCE

AI prompts with governance context

Turn structured program evidence into executive-ready analysis—without inventing facts.

EXECUTIVE REPORTING

Weekly SteerCo brief

Convert priorities, decisions, escalations and milestone changes into five executive bullets with owners and required actions.

RISK CONTROL

RAID challenge

Challenge the stated mitigation, surface missing dependencies and identify the earliest decision point that changes exposure.

UAT READINESS

Go / No-Go evidence

Assess open Sev 1 and Sev 2 defects, test capacity and exit criteria against the planned deployment gate.

CHANGE & ADOPTION

Stakeholder intervention

Prioritize resistant or disengaged stakeholders by business impact and propose accountable interventions.

Operating safeguard

Human approval remains the decision boundary

TCC Intelligence produces analysis and drafts. Program owners approve status, decisions, escalations, pricing, contracts and every external communication.

Human-in-the-loop